June 18, 1998
- Mr. Russell J. Harding, Director
- Department of Environmental Quality
- P.O. Box 30473
- Lansing, MI 48909-7973
Dear Mr. Harding:
Thank you for your June 8 response to my May 15 letter to Governor Engler
regarding issues at three sand dune mines in Covert Township, Van Buren
County. We look forward to your item by item response to our observations
and findings. Part 301 Permit
I must correct one of your statements. Based on information provided
by the Land and Water Management Division, the permit to dredge a lake at
the Nadeau Pit expired December 31, 1993, not August of 1995. The permit
was issued to Manley Brothers on August 3, 1990. If there is documentation
of a later date or of TechniSand ever being issued a permit we would appreciate
receiving a copy. Observed Changes at Nadeau Pit
A recent visit to the Nadeau Pit revealed that a number of needed corrections
are underway or have been completed. For example,
- The unused/abandoned mining equipment that had been left in reclaimed
Cell Unit 1 has been relocated to the plant area.
- About 100 feet of fencing has been added (as your letter indicated)
at a popular entry point for ORV's. Make shift fencing has been also added
for 6 or 8 feet south of the North Gate.
- Grading and spreading topsoil at the eastern portions of Cell Units
8 (which as far as we are aware has never been put in active status), 7,
and 5 is proceeding.
We hope that these actions are an indication that your department is
finally beginning to require compliance with the statutes by TechniSand
at the Nadeau Pit.
Surveyed Boundaries
We observed that, as reported in your letter, the corners of a number
of the Cell Units have been surveyed and marked. We request that the DEQ
response to our letter include survey coordinates of the Cell Unit boundaries,
and a copy of a scaled site plan indicating the points located by survey
and certified by the professional surveyor who conducted the survey. This
is very important for several reasons.
- The Cell Unit boundaries in the past have only been lines on a site
plan. There is no precedent for the surveyed locations. Without coordinates
and a corresponding scaled drawing the surveyed locations become just another
version of the site map. With coordinates, these locations can be relocated
with precision and areas calculated accurately.
- There are apparent discrepancies between the stake locations and the
overlay plans previously prepared by TechniSand and furnished to us under
the FOIA by the DEQ. For example, it appears that the boundary between
Cell Unit 8 and 2 is at least 50 feet south of that shown on the plans
previously submitted by TechniSand, and the boundary between Cell Unit
10 and 3 is an extension of that line.
- In the past TechniSand has misled the DEQ (e.g., when Cell Unit 4 of
the Busse Property was enlarged to include adjacent land).
- TechniSand has a poor reputation for honesty and forthrightness. The
public does not trust TechniSand.
We also request a copy of the current Progressive Cell Unit Mining and
Reclamation Plan. We understand that Amendment 6, dated April 1997 has been
rescinded due to the encroachment on the buffer area at the Thunder Mountain
Heights property. Furthermore, the Van Buren County Road Commission has
notified us that it has rescinded its permission to include portions of
the right of way of the Blue Star Highway in the mine site.
Additional Questions
The February 6 response by Mr. Fitch to our December 18, 1997 letter
documenting violations raised numerous questions that we hope will be answered
in the upcoming response.
- No conformance bond is required for the Plant Area. Why not? It is
20 acres plus roads and slurry lines. When land was transferred from other
Cells to create the Plant Area, the DEQ released this un-reclaimed land
from bonding requirements. What assurances does the public have that the
operator will reclaimed this area?
- The DEQ requires that slopes be no steeper than 1:3 as required by
amendments to the statute instead of 1:2 allowed when original permit was
issued for the mine in 1978. Yet the DEQ does not require that setbacks
to be increased to 200 feet as the law requires, even when the Cell Unit
boundaries are changed for the convenience of the operator by an amendment
to the Progressive Cell Unit Mining & Reclamation Plan. Why not?
- When a permit is originated, the operator's application includes the
Progressive Cell Unit Mining and Reclamation Plan. This plan is discussed
at public hearings and is used to "sell" the mining of a site
to neighbors. In the plan the operator makes very specific commitments
regarding the reclamation of the land. After the permit is issued, the
reclamation requirements are continually reduced by agreement between the
DEQ and the mine operator without public review and comment. Why is this
allowed?
Special Condition 9 of the permit states "The Department, upon written
application from the permittee and a public hearing, may modify or permit
variance from the progressive cell unit mining and reclamation plan or
special permit conditions if such modification or variance is not contrary
to the public interest and in accordance with the Administrative Procedures
Act (Act No. 306, P.A. 1969 as amended." We know of no public hearings
to revise the PCUMRP. Were they held? If so, where was public notice made?
Can we have copies of such notices?
- In addition to other requirements, 63712(5) requires that no single
area of exposed sand shall be greater than 25 square feet, and final grades
no steeper than 1:3 must be established in order for a cell to be placed
in interim status. Yet the DEQ has accepted a Cell Unit as being in interim
status that does not fully comply with these requirements. Why?
- The DEQ does not require a current Fifteen-year Mining Plan as required
by 63704(d) and prescribed by 63707 when permits are issued. Why?
- As we read the statute, until a Cell Unit becomes active it cannot
be used for mining operations. This is further validated by Special Condition
4 which states "The permittee shall confine all vehicles and equipment
to the limits of active cell units...." How has TechniSand been allowed
to have a roadway through Cell Units 10, 11 and 8 when these Cell Units
have never been placed in active status?
- The DEQ released Cell Unit 2 from conformance bond requirements. It
was revegetated with dune grass a number of years ago. The PCUMRP requires
trees to be planted. Will the trees ever be planted? If so, what assurances
are there?
- How does the DEQ justify allowing a dredging activity to be carried
out when no permit is in effect? Quoting the letter from Mr. Thomas Fette,
our attorney, dated May 7 to the Land and Water Management office in Plainwell:
"TechniSand's inland lakes and streams permit expired on December
31, 1993. It did not seek a renewal prior to expiration, but nevertheless
continued its activities thereafter. In 1995, some two years after its
permit lapsed, TechniSand purportedly made some type of request to the
department to extend the expired permit, though we have seen no documentation
relating to this request and do not know whether the request was in the
form of an application, as is required by Section 30104 of Part 301. The
department had at least constructive notice that TechniSand was violating
Part 301 as of the end of 1993 and it had actual notice of the violation
in 1995, and yet did nothing to enforce the law.
"In a memorandum dated February 6, 1998, to Harold R. Fitch, Chief
of the Department's Geological Survey Division, Rodger Whitener and Douglas
L. Daniels responded to a letter from Preserve the Dunes, Inc. dated December
18, 1997, which had raised a number of concerns relating to TechniSand's
activities. In that memorandum the authors concluded that 'usually, more
operations are allowed to continue during the permit renewal process, as
long as the company operates in compliance with the previous permit conditions.'
The authors also stated 'we believe the operator is allowed to continue
to operate under the existing permit until the DEQ takes affirmative action
to revoke the permit.' These statements are both factually and legally
incorrect. First, there was no permit review process in existence until
1998. During that four year period the Department permitted TechniSand
to conduct unpermitted activities. Second, there was no 'existing' permit.
It had expired at the end of 1993. Third, and most important, the law does
not allow continued operations 'until the DEQ takes affirmative action
to revoke the permit.' Section 30107 of Part 301 specifically provides
'a permit is effective until revoked for cause but not beyond its term
and may be subject to renewal.' Because a permit is valid only during its
term there is no legal justification for the department having allowed
operations to continue once the permit expired.
In our view the mandate of the law is clear. The department must immediately
order TechniSand to cease and desist any further operation which may effect
or enlarge the existing Nadeau Pit pond unless and until a proper permit
is issued."
The obligation to acquire a Part 301 Permit is clearly placed on the
operator and emphasized in Special Condition 10 of the Permit which states
"The permittee shall not remove sand from below the water table at
this site, thereby creating a body of water, without obtaining a permit
under Part 301 ...."
Finally, we request that the DEQ respond be to our statement sent to
Governor Engler and dated May 15 rather than the response dated February
16, 1998. I have enclosed a copy for your use.
Thank you for your attention to these matters.
Sincerely,
-
-
- Charles F. Davis, III President
- Enclosures
-
- cc:
- Governor John Engler
- The
Honorable Harry Gast, State SenatorDistrict 20
- The
Honorable Robert Brackenridge, State RepresentativeDistrict 79
- The
Honorable James Middaugh, State RepresentativeDistrict 80
- Mr. Jerry Sarno, Covert Township Supervisor
- Mr. Michael Leffler, Assistant Attorney General
-
TOP | BACK
© Preserve the Dunes, Inc.
P.O. Box 581, Riverside, MI 49084
Write us